Due Diligence · Audits · Contract Review · Project Delivery
Connectivity, from due diligence to delivery.
I run the connectivity scope on build-outs, audits and migrations — as your owner’s rep, not the contractor. You hold the contracts; I take no markup.
The problem
The building decides your timeline
Typical infrastructure lead times, in days. Whether you’re opening a new location, expanding bandwidth, or adding circuit redundancy, telecom lead times are the unmovable dates that decide your schedule.
Open end: permits and moratoriums have no fixed ceiling
| Item | Lead time |
|---|---|
| New Fiber Build | 90–120+ days, plus permitting |
| On-Net Fiber Activation | 35–65+ days |
| Bandwidth Upgrades | 10–45+ days |
| MDF Readiness & Structured Cabling | 30–60+ days |
A new fiber build runs 90 to 120 days — and that is before permits. City permitting can add months, and seasonal moratoriums can stop work from starting even when the approval is already in hand.
So the answer isn't ordering earlier. It's finding a provider already on-net in the building, where there's little or no build work to do at all.
That question is worth answering before you sign the lease — not after.
And on-net activation is still five sequential steps
- 1Order placed & processed1–2 wk
- 2Site survey completed1–2 wk
- 3Engineering SOW issued1–2 wk
- 4Fiber pulled & spliced1–2 wk
- 5NID installed & circuit activated1 wk
Steps 4 and 5 wait on the MDF — and the MDF waits on the room
A carrier will not splice into a dusty, half-built room, so none of it counts until the space is genuinely finished.
Low-voltage work is rarely what holds this up. The vendor starts early, pulls cable into the IT room and leaves it coiled, and sets the rack — they simply can't terminate until that rack is in. The real constraint is the construction happening around them: drywall, drop ceiling, and the electrical work.
What “MDF ready” actually means
- Power and outlets at the rack
- IT rack in place and bolted to the floor
- Plywood backboard mounted for the carriers
- Ventilation in place, or close to it
Which means your activation date is set by somebody else's drywall schedule. That seam between the trades is the one nobody owns, and it is where dates get lost.
21 to 42 days before a scope of work even exists, and 35 to 65 days in total when nothing goes wrong. None of it starts until the order is placed, and every step waits on the one before it — so a delay anywhere moves the activation date.
We manage the carrier milestones and coordinate the physical trades so you never lose weeks waiting on the seam between them.
What I do
Five reasons people call me
Carrier Availability Check
Which carriers genuinely serve a building — with real pricing. Not a coverage map.
Send any address, an existing site or one you’re considering. Within 48 hours you get the carriers actually serving that building — on-net, near-net or unavailable — real pricing at the bandwidths you need, near-net construction costs where they apply, and install lead times.
No charge, no obligation. If you order a circuit you hold the contract directly with the carrier. I’m a telecom agent as well, so the carrier compensates me, not you — and if you don’t order, you still have the answer.
Pre-Lease Infrastructure Due Diligence
What it will actually cost to stand up each building you’re considering — before you sign.
Carrier availability and real pricing per candidate building. Riser and pathway capacity to your target floors, and whether it’s already allocated. MPOE and demarc location. Lead time against your opening date, and what has to start before signature. A deployment cost estimate, not just a circuit cost. Delivered as a side-by-side comparison with a recommendation.
Plus what to put in the LOI — riser access rights, conduit allocation, carrier entry, and who pays to build pathway. Cheap before signature, effectively unobtainable afterwards.
Physical Infrastructure Audit
Run it before a migration — or before an enterprise tenant’s IT team runs it for you.
A full walk of a building you already operate. MDF, every IDF, the floor, every port, every AP, and the carrier demarcs traced from the NID to the equipment. Hardware inventory with EoL and EoS status. Patch panel labels verified. Cabling grade and what it can carry. PoE budgets. Power and cooling against planned load. Rogue tenant gear identified.
Prioritised findings with remediation costs, and a value summary: avoided spend, sellable capacity, and risk closed before cutover.
The two numbers that surprise people: what the IT room can safely power, and what the circuits on the monthly bill are costing against what’s actually being delivered.
Telecom & Technology Contract Review
Most operators can’t produce a list of every circuit they pay for. That isn’t anyone’s fault.
A complete service register across the portfolio — carrier, service ID, bandwidth, MRC, NRC, term, contract end, notice window. Renewal exposure with dates, and what’s sitting on auto-renew. Bandwidth against actual utilisation. Voice seats and DIDs against actual users. A portfolio re-bid against current market rates, and a plan to pull scattered end dates coterminous.
The fee is a share of the savings you actually realise, agreed before I start. Find nothing, owe nothing.
IT Infrastructure Project Delivery
Your GC manages forty line items and connectivity is one of them, usually scoped last.
The connectivity scope of a build-out, migration, refresh or expansion, end to end. Requirements and design oversight. Carrier procurement through delivery. Vendor selection and management. Schedule ownership against the opening date. COI and site access coordination. Cutover run-of-show and night-of oversight. Verified delivery with test evidence, not “configured”.
Documented handover: circuit register, room-and-port documentation, network diagrams, as-builts, escalation contacts.
Physical work is performed by licensed, insured low-voltage contractors. You choose them, you hold those contracts, and I take no markup on their work.
What I own, and what I don't
One schedule. One scope. One point of accountability.
You hold the contracts — the low-voltage vendor, the hardware, the carrier. I hold the scope and the schedule — design review, carrier coordination, sequencing, the cutover itself, and the closeout documentation you keep afterwards. If you don't already have a vendor you trust, I'll run a competitive bid and you pick. I take no markup either way, and Layer 3 and configuration management stays with your internal IT team or MSP.
And if the schedule says the circuit won't land in time, I'll arrange a temporary connection so you open on the date you announced. That call has its own deadline — made too late, it doesn't help either.
The alternative is managing three vendors, two carrier installations, and separate cabling timelines yourself — and finding out too late which one pushed your delivery date.
About
Vincent Carminati
I've spent the last twelve years in telecom infrastructure, most recently leading IT infrastructure and telecom delivery for coworking operators across hundreds of sites.
Line of Sight exists because connectivity is the piece your Go Live date depends on, and it is the piece with the least slack in it. Everything else on a build-out or a hardware cutover can absorb a day or two. An unmanaged circuit timeline cannot.
Which is why the schedule is the deliverable. Cable and circuits are the known quantity — sequencing them against a date that can't move is the actual job. It's why the first question I ask anyone is when they need to be in the space.
1,000+ internet circuits delivered. 200+ circuit migrations across North America. 50,000+ voice lines migrated across 300+ commercial and flex sites. Which means I've also seen most of the ways a build-out goes wrong.
At essensys I scaled U.S. expansion as the sole pre-sales engineer, supporting over a hundred new site openings a year and owning the capex and opex infrastructure scope on every one of them.
MBA · PMP Certified — full history on LinkedIn.
Contact
Send me an address
Tell me the building — or buildings — you're looking at and I'll come back with real pricing from the carriers that actually serve it — what it costs, whether it's on-net or a new build, and how long it will take. No charge and no obligation.
If you have a target occupancy date, project deadline, or contract renewal coming up, include it — that's the anchor everything gets planned around.
On-net pricing comes back inside 48 hours. If the building needs a near-net build, the carriers have to respond and that takes a few days — I'll tell you which one you're dealing with up front.